Liberty Building Cx

Leeds, Massachusetts | US Department of Veterans Affairs

The US VA chose to construct an addition and renovate space in B1 (main campus building) to house a new primary care suite at the Central Western Massachusetts VA Medical Center. To accommodate hospital protocols, D&K’s commissioning team, the design consultant, and the contractor advanced the project using phased construction. For the mechanical and DDC control systems, D&K commissioned each phase, including control and balancing to meet applicable codes and support occupancy and use in the interim configurations. The control system was upgraded so that the graphics and programming required verification for the new HVAC equipment. Equipment included AHUs, humidifiers, VAVs, reheat devices, and related controls.

Service Areas:
Markets:

Project Elements

• The project added and improved approximately 16,000 SF
• To minimize disruption to the facility, the project was phased.